CLIENT CONTRACTOR PLANT LOCATION APPLICATION DUTY / CAPACITY SCOPE YEAR OF
COMPLETION
Valero Jacobs Aruba Two Visbreaker Furnace Coils 87 x 2 MMBtu/hr EP 2005
ChevronPhillips JGC Jubail, Saudi Arabia Alkylator Reboiler 93 MMBtu/hr EP 2005
ChevronPhillips JGC Jubail, Saudi Arabia Styrene Steam Superheater 245 MMBtu/hr EP 2005
Suncor Jacobs Denver, CO Fractionator Heater Revamp 27.28 MMBtu/hr EP 2005
Suncor Jacobs Denver, CO Vacuum Charge Heater 4 MMBtu/hr EP 2005
Suncor Jacobs Denver, CO Vacuum Charge Heater 5.3 MMBtu/hr EP 2005
Suncor Jacobs Denver, CO Crude Preheat 32.54 MMBtu/hr EP 2005
Suncor Jacobs Denver, CO Crude Heater 21.9 MMBtu/hr EP 2005
PetroCanada Bantrel Montreal, Canada Revamp of Crude Furnace Floor 65 MMBtu/hr EP 2004
Suncor Jacobs Denver, CO Recycle Gas Heater 34.88 MMBtu/hr EPC 2005
Suncor Jacobs Denver, CO Fractionator Feed Heater 27.83 MMBtu/hr EPC 2005
Braskem KTI Halagaos, Brazil New EDC Pyrolysis furnace 60 MMBtu/hr EP 2005
Shell Canada Colt Sarnia, Canada New (1) Cell CCR Heater 23 MMBtu/hr EP 2005
ConocoPhillips KTI Ponca City, Ok Revamp CCR, Vacuum & reboiler heaters for NOx reduction 100, 68, 44 EPC 2004
Flint Hills Refining/Koch Jacobs Corpus Christi, Tx Revamp UOP Platformer NOx and Capacity 600 MMBtu/hr EPCM 2004